    Principio de transparencia y selección objetiva en el contrato de obra pública de la fase III de Transmilenio y acciones legales que se llevaron a cabo para su terminación

    Thumbnail
    View/Open
    Transparencia_selección_objetiva_Transmilenio.pdf (Trabajo de grado) (744.7Kb)
    Documentos trabajo de grado para biblioteca Universidad La Gran Colombia.pdf (Carta de autorización) (4.162Mb)

    Date

    2015

    Author

    Farfán Mejía, Tania Liseth
    Mosquera Vargas, Martha Liliana

    Título obtenido

    Especialista en Derecho Administrativo

    Director de tesis

    Pérez Ferro, Luis Carlos

    Publicador

    Universidad La Gran Colombia

    Facultad

    Facultad de Postgrados

    Programa

    Especialización en Derecho Administrativo

    Citación

           
    Share
    TY - GEN T1 - Principio de transparencia y selección objetiva en el contrato de obra pública de la fase III de Transmilenio y acciones legales que se llevaron a cabo para su terminación AU - Farfán Mejía, Tania Liseth AU - Mosquera Vargas, Martha Liliana Y1 - 2015 UR - http://hdl.handle.net/11396/3737 PB - Universidad La Gran Colombia AB - It sought to establish with the present investigation, the review of each and every one of the principles that on government procurement ruled for the construction and commissioning of public works of Transmilenio Phase III stretch of 26th Street, a study from reading several newspaper articles, case law, statutes, reports control entities, allowed disaggregate information to conclude that entailed the development and execution of the contract No.137 of 2007. It also allows to recognize the shortcomings of public works since state pre-contractual, contractual and post-contractual, ending in a session since the initial contract signed did not meet satisfactory, leaving part of the population of the city of Bogota in traffic chaos, because mobility problems this section large influx was affected directly from the start of construction of this street. We further conclude that the administration at the time, was plunged into a series of tax, disciplinary and criminal processes, with results that are still to be decided and to light have been a few who have been sanctioned for such activity. As well as the incalculable losses that the public has known for the various media and reports that both the Comptroller and the Attorney forward on this issue and that apparently is still indebted to the firm, by assignment, could culminate it. ER - @misc{11396_3737, author = {Farfán Mejía Tania Liseth and Mosquera Vargas Martha Liliana}, title = {Principio de transparencia y selección objetiva en el contrato de obra pública de la fase III de Transmilenio y acciones legales que se llevaron a cabo para su terminación}, year = {2015}, abstract = {It sought to establish with the present investigation, the review of each and every one of the principles that on government procurement ruled for the construction and commissioning of public works of Transmilenio Phase III stretch of 26th Street, a study from reading several newspaper articles, case law, statutes, reports control entities, allowed disaggregate information to conclude that entailed the development and execution of the contract No.137 of 2007. It also allows to recognize the shortcomings of public works since state pre-contractual, contractual and post-contractual, ending in a session since the initial contract signed did not meet satisfactory, leaving part of the population of the city of Bogota in traffic chaos, because mobility problems this section large influx was affected directly from the start of construction of this street. We further conclude that the administration at the time, was plunged into a series of tax, disciplinary and criminal processes, with results that are still to be decided and to light have been a few who have been sanctioned for such activity. As well as the incalculable losses that the public has known for the various media and reports that both the Comptroller and the Attorney forward on this issue and that apparently is still indebted to the firm, by assignment, could culminate it.}, url = {http://hdl.handle.net/11396/3737} }RT Generic T1 Principio de transparencia y selección objetiva en el contrato de obra pública de la fase III de Transmilenio y acciones legales que se llevaron a cabo para su terminación YR 2015 LK http://hdl.handle.net/11396/3737 PB Universidad La Gran Colombia AB It sought to establish with the present investigation, the review of each and every one of the principles that on government procurement ruled for the construction and commissioning of public works of Transmilenio Phase III stretch of 26th Street, a study from reading several newspaper articles, case law, statutes, reports control entities, allowed disaggregate information to conclude that entailed the development and execution of the contract No.137 of 2007. It also allows to recognize the shortcomings of public works since state pre-contractual, contractual and post-contractual, ending in a session since the initial contract signed did not meet satisfactory, leaving part of the population of the city of Bogota in traffic chaos, because mobility problems this section large influx was affected directly from the start of construction of this street. We further conclude that the administration at the time, was plunged into a series of tax, disciplinary and criminal processes, with results that are still to be decided and to light have been a few who have been sanctioned for such activity. As well as the incalculable losses that the public has known for the various media and reports that both the Comptroller and the Attorney forward on this issue and that apparently is still indebted to the firm, by assignment, could culminate it. OL Spanish (121)
    Gestores bibliográficos
    Refworks
    Zotero
    BibTeX
    CiteULike

    Palabras clave

    Contratación estatal
    Obra pública
    Contratos
    Movilidad
    Transmilenio
    Contratos públicos - Estudios de casos
    Transporte urbano - Aspectos jurídicos - Bogotá (Colombia)
    Responsabilidad administrativa
    Metadata
    Show full item record

    Abstract

    Se pretendió establecer con la presente investigación, la revisión de todos y cada uno de los principios que en materia de contratación estatal rigieron para la construcción y puesta en marcha de la obra pública Fase III de Transmilenio, tramo de la calle 26, estudio que desde la lectura de varios artículos periodísticos, jurisprudencia, leyes, informes de entes de control, permitieron desglosar información que conllevaron a concluir sobre el desarrollo y ejecución del contrato No.137 de 2007. Así mismo permite reconocer las falencias de la obra pública desde su estado precontractual, contractual y pos contractual, terminando en una cesión de contrato por cuanto la firma inicial no cumplió a satisfacción, dejando a una parte de la población de la ciudad de Bogotá con grandes inconvenientes de movilidad. Concluimos además, que la administración de ese entonces, se vio inmersa en una serie de procesos de tipo fiscal, disciplinario y penal, con resultados que aún están por decidirse y que a la luz pública han sido unos pocos quienes se han visto sancionados por tal actividad. Así como también las pérdidas incalculables que la ciudadanía ha conocido por los diferentes medios de comunicación y los informes que tanto la Contraloría como la Procuraduría adelantaron sobre este tema y que al parecer, aún se encuentra en deuda con la firma que, por cesión, pudo culminarla.

    Abstract

    It sought to establish with the present investigation, the review of each and every one of the principles that on government procurement ruled for the construction and commissioning of public works of Transmilenio Phase III stretch of 26th Street, a study from reading several newspaper articles, case law, statutes, reports control entities, allowed disaggregate information to conclude that entailed the development and execution of the contract No.137 of 2007. It also allows to recognize the shortcomings of public works since state pre-contractual, contractual and post-contractual, ending in a session since the initial contract signed did not meet satisfactory, leaving part of the population of the city of Bogota in traffic chaos, because mobility problems this section large influx was affected directly from the start of construction of this street. We further conclude that the administration at the time, was plunged into a series of tax, disciplinary and criminal processes, with results that are still to be decided and to light have been a few who have been sanctioned for such activity. As well as the incalculable losses that the public has known for the various media and reports that both the Comptroller and the Attorney forward on this issue and that apparently is still indebted to the firm, by assignment, could culminate it.
    URI
    http://hdl.handle.net/11396/3737
    Collections
    • Especialización en Derecho Administrativo [267]
    Guías de uso Guía de autoarchivoCarta de autorización de publicación

    Browse

    All of DSpaceCommunities & CollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

    My Account

    LoginRegister
    Universidad La Gran colombia
    Universidad La Gran Colombia - Biblioteca
    Biblioteca UGC - Koha
    Creative Commons

     


    Universidad La Gran Colombia - Bogotá D.C. Colombia.
    Cra 6 No. 12B - 40. PBX: 3276999
    DSpace software copyright © 2002-2016  DuraSpace
    Contact Us | Send Feedback